CS615- Software Project Management
Quiz No.1
Dated: 17th April 20120
…………. theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins.
Select correct option:
Project life-cycle-based
Scheduled
None of given
Deliverable-based
Predecessor activities need to ------------ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity.
Select correct option:
Both start and end
End
Start
None of given
Each …………. can be subdivided into sub tasks.
Select correct option:
None of given
Program
Task
Project
Using PERT and CPM, -----------------------, helps you complete a project on time. By using these techniques, you can determine the latest time by when an activity should start to be completed on time.
Select correct option:
Individually
Combination
Individual and Combine (handouts, page 296)
None of given
Over the course of the project, a comparison of the due date and the date delivered provides a metric for how well deliverable dates are ………………. by the project team.
Select correct option:
Met
Scheduled
None of given
Changed
Risk analysis and management are a series of steps that help a software team to understand and manage ------------------------.
Select correct option:
Uncertainty
Crises
none of given
Problem
A node on a network schedule is that point in time at which an activity ----------------.
Select correct option:
Begins
Begins or Ends (handouts, page 297)
Ends
None of given
To ------------------- risks from occurring, the project team prepares the risk plan before the commencement of the project.
Select correct option:
Avoid (handouts, page 312)
deal
None of given
Manage
Like all engineering disciplines, requirements engineering is not conducted in a
Sporadic random
Otherwise haphazard fashion
But instead is the systematic use of proven approaches?
All of given
_____________ includes consideration such as the post-implementation support activities provided to the customer.
Training plan creation
User acceptance plan
Implementation plan creation
Support plan creation
Requirements are refined and analyzed to assess their clarity, completeness, and_______
Correctness
Consistency
Concurrency
None of given
__________ defines the duration of implementation and the hard and software perquisites for implementing the software product.
Training plan creation
User acceptance plan
Implementation plan creation
Support plan creation
Implementation of software quality often associated with
Project Manager - unconfirmed
Software developer
Customer
User
A software project that meets all the stated objectives is a success of _________
Project quality
Project fundamental purpose
Project management myth
Project requirement
Throughout evaluation and solution synthesis, the analyst's primary focus is on ________
Select correct option:
"Not what, not "how"
"What, also "how"
"What, not "how"
None of given
Like all engineering disciplines, requirements engineering is not conducted in a
Select correct option:
Sporadic random
Otherwise haphazard fashion
But instead is the systematic use of proven approaches?
All of given
The Project Planning, Controlling and Tracking includes Task
elect correct option:
Detailed Project Plan
Scope determination
initial project plan
Requirement gathering
Unstructured and hurried software development is a
Technology-related problems
Product-related problems
Process-related problems
People-related problems
A software project that meets all the stated objectives is a success of _________
Select correct option:
Project quality
Project fundamental purpose
Project management myth
Project requirement
We can classify the problems that affect software projects into _______ categories
3
4
5
6
4
Software requirements engineering is a process of all except
Select correct option:
Discovery
Refinement
Design
Specification
Unproductive work environment is a
Select correct option:
Technology-related problems
Process-related problems
People-related problems
Product-related problems
Both the software engineer and customer take an active role in software requirements engineering-a set of activities that is often referred to as
Analysis
Design
Specification
System acceptance
All of the following are types of project closures or endings except:
Addition
Integration
Verification
Extiction
Project Quality Management includes the --------------- required to ensure that the project will satisfy the needs for which it was undertaken
Select correct option:
Time
Cost
None of the given
Zindagi mein 2 Logo ka buhat khayal rahkoooo
2nd woh jiss ko tum ney har dukh me pukaara hoo (Mother)
--
Please visit http://vusr.net for Old and Latest Papers, Assignments, Quiz and GDBs.
http://VUSR.net The ultimate VU Study Resource
You received this message because you are subscribed to the Google
Groups "VUSR" group.
To unsubscribe
vusr+unsubscribe@googlegroups.com
To Visit Group Home Page
http://groups.google.com/group/vusr?hl=en?hl=en
No comments:
Post a Comment